Don't blame us for Aquatic Centre delay: Contractor

On May 15, 2014, there was still no roof for the Aquatic Centre of the Kangar Sports Complex.
On May 15, 2014, there was still no roof for the Aquatic Centre of the Kangar Sports Complex.

KANGAR: Now that the Malaysia Games (Sukma) have been launched and the State Aquatic Centre is still not ready, the finger-pointing and blame-shifting has begun.

Perlis Mentri Besar Azlan Man and Youth and Sports Minister Khairy Jamaluddin had earlier said that the venue would be ready in time.

On Friday, National Sports Council director-general Datuk Seri Zolkples Embong echoed their sentiments. He gave his assurance that the State Aquatics Centre would be ready in time for the Sukma aquatics competition.

On Monday, the centre still did not look ready. What's worse, the water filtration pump for the diving pool was being repaired midday on Monday following some issues which turned the pool's water murky. In addition, there was still paint work and side jobs still being conducted.

Main contractors Lima Corporation said they are not to be blamed for the delay in completing the State Aquatic Centre.

The contractors, who were roped in to refurbish the centre, have come under fire from all parties as the swimming and diving events are set to take place in less than 48 hours.

“We won the tender in July last year but only got the approval to build in January and started construction in February this year. So don't blame us for the delay,” said Lima Corporation's operations director Hishamuddin Abdul Hamid.

Federal Territories' diving team manager Lee Keah Chang lamented the condition of the centre.
Arriving on Sunday, the team had hoped to train early but the pool was not fit to be used.
“Usually, aquatic venues would have been ready 10 days before a competition. This is less than 24 hours. It just looks unprepared,” said Keah Chang.

“Then there is the issue of both the 3m and the 10m platforms which are seen to be overlapping each other which is against FINA (International Swimming Federation) rules,” he continued.

Contractor Hishamuddin however insisted that the platforms overlapped within the permitted limit.
Keah Chang feels that if the Aquatics Centre is to be ready by competition day, which is Wednesday, then the organisers and contractors need to act fast.

“I'm worried for the athletes. They are our main priority and concern,” added Keah Chang on Monday, before the team left to train at the Gunung Keriang Aquatics Complex in Alor Setar, Kedah.
Meanwhile, Amateur Swimming Union of Malaysia (ASUM) secretary Edwin Chong was reluctant to be drawn into the issue.

“All the teams are already here and they've checked into the Games Village or hotels so it is a little disruptive to team preparations,” he added.

“But we're hoping they'll get it ready in time. Every Sukma venue is bound to have some minor or major problems. I think this is a solvable issue.”





Comments

Popular posts from this blog

Ex-coach's jail sentence cut to a year

PUTRAJAYA: The Court of Appeal yesterday sentenced former athletics coach C. Ramanathan to 12 months' jail for molesting two junior athletes 19 years ago. A three-man bench led by Datuk Mohd Hishamudin Mohd Yunus unanimously dismissed Ramanathan's appeal against conviction, but varied the jail sentence of four years to a year, which was to run concurrently. Following yesterday's ruling, Ramanathan, 75, a former teacher, walked out a free man as he had served 10 months in Kajang Prison. Convicts get one-third remission for good behaviour while in prison. However, he will lose his pension. Hishamudin, who sat with Datuk Abdul Wahab Patail and Datuk Linton Albert, said the court found no merit to overturn the conviction. "However, in reducing the sentence, we considered Ramanathan's age and the long years the appeal has taken." Deputy public prosecutor Awang Armadajaya Awang Mahmud submitted that then High Court judge Tan Sri Abdull Hamid E...

Govt Always Gives Emphasis To Sporting Culture, Says PM

KUALA TERENGGANU, May 29 (Bernama) -- Datuk Seri Abdullah Ahmad Badaw i said the government always gives emphasis on cultivating a strong sporting culture in achieving excellence at the international level. As such, the Prime Minister said, it was important to scout for young talents in sports. "I observe that the Malaysia Games (Sukma) has become one of the important platforms to do so. "In this arena, the potentials and skills of the youngsters can be identified for development so that they can achieve greater success in sports," he said in his message in the souvenir book of the 12th Sukma from May 31 until June 9. Abdullah said he was aware that competition in sports was very keen and challenging but this did not mean that Malaysian athletes were incapable of competing at the international level. "The fact is that we have all the characteristics required to be excellent. We must inculcate a strong fighting spirit so that we don't easily surrender,...

Rajagobal Let Off The Hook

PETALING JAYA, April 24 (Bernama) -- National head coach Datuk K. Rajagobal was let off the hook by the Football Association of Malaysia's (FAM) Disciplinary Committee after finding no evidence that he had violated FAM's Article 88, as claimed. FAM Disciplinary Committee chairman Datuk Taufik Abdul Razak said the committee had decided not to charge Rajagobal after carefully analysing the video of the post-match press conference by the 56-year-old coach. "After listening to the recording of the post-match press conference, we decided to drop the charge against Rajagopal as he did not make such a statement. "Maybe his (Rajagobal) assessment and comments of the match was misconstrued by the media. There was no mention of the FAM policy throughout his comments," said Taufik after emerging from a three-hour Disciplinary Committee meeting at Wisma FAM in Kelana Jaya, here, Wednesday. Rajagobal who does not mince his words when asked to com...